Fulfilling Safety Requirements for International Oil and Gas Company

British Petroleum or better known as BP, is one of the world's leading integrated Oil & Gas companies. They provide fuel for transportation, energy for heat and light, and lubricants all over the world. In Indonesia, BP operates all of its main business streams and has established its presence since 2009. One of its biggest project in Indonesia known as Tangguh LNG project that constitutes the development of six gas fields in the Wiriagar, Berau and Muturi Production Sharing Contracts (PSC) in Bintuni Bay, Papua Barat.

Tangguh LNG produces natural gas thus all equipments and tools must comply with rather stringent explosion proof classification, coupled with BP's requirement for EHS (Environment Health Safety) and business processes where acquisition of top quality product via a reliable crane supplier was deemed very imperative.

MHE Demag Indonesia's know how,  product superiority & broader service network capacity qualified us to meet above said criteria, and created an avenue to gain BP's trust that had led us to win such prestigious project tender. Our team has been given a platform to display a sterling performance to demonstrate its competence that ensured  MHE Demag Indonesia to successfully penetrate into BP business for the first time in the history.

In this project, our scope of our supply consists of two units of 10 tons complete ATEX certified explosion proof cranes, and both cranes will be used for periodical maintenance in the natural gas production plant in the process of assembling and disassembling of the gas turbine components. Since the production shut down time for maintenance is very tight, speed is seen of the essence, hence  BP's maintenance division can't afford to encounter any breakdown during the plant shut down period. With MHE's Ex proof cranes, this particular expectation was managed very well, and plant maintenance division succeeded to carry out its duty without any setback.  

 

The BP Tangguh project execution began last year in September 2015 and was completed in April 2016. We can proudly say, the cornerstone of our success was profoundly on the basis of our country specific ex proof strategy, coupled with highly productive team work between Regional Ex Proof Team and MDI since the early stage of the tender.

 